According to the question The first 10 days she did only 1/30 of the work on each day = (10 × 1/30) =1/3 The remaining work = (1-1/3) = (3-1)/3 = 2/3 Now, Time taken to complete a task by Ruchira in 12 days = [(1/ (22-10) × 2/3] = (1/12 × 2/3) =1/18 The required work is 18.