A group of 6 workers can complete a project in 12 days.
However, due to unforeseen circumstances, 2 workers had to leave after 3 days.How many additional days will it take for the remaining workers to complete the project?Solution
Total work required: 6 workers × 12 days = 72 worker-days Work done in 3 days by 6 workers: 6 workers × 3 days = 18 worker-days. Remaining work after 3 days: 72 worker-days - 18 worker-days = 54 worker-days. Remaining workers after 3 days: 6 workers - 2 workers = 4 workers. days needed for 4 workers to complete the remaining work: 54 worker-days ÷ 4 workers = 13.5 days. Additional days = 13.5 – 9 = 4.5 days
What is the theme of the IICA North-East Conclave 2025 held in Shillong?
Which peafowl species is classified as Near Threatened by the International Union for Conservation of Nature ( IUCN) ?
Which day is observed as Hindi Journalism Day?
Which city is set to host the 2025 Asian Youth Para Games?
What is the revised interest rate offered to super-senior citizens under SBI’s Amrit Vrishti FD scheme from April 15, 2025?
Which two initiatives were virtually inaugurated by Union Minister Shri Dharmendra Pradhan?
What is the primary objective of the PAN 2.0 Project by the Income Tax Department?
- Who won the Best Actor Award at the 2025 National Film Awards?
What is the title of the book launched by retired IPS officer V.S. Ravi?
What new digital initiative did the Government of India launch to manage business documents?