πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      P can do Β½ of a work in 10 days and Q can do 1/5 of the

      same work in 4 days. In how many days can both finish the work, working together?
      A 15 days Correct Answer Incorrect Answer
      B 14 days Correct Answer Incorrect Answer
      C 10 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer

      Solution

      P can do Β½ of a work in 10 days. So P can do the whole work in 10x2 = 20 days. Q can do 1/5 of the same work in 4 days. So Q can do the whole work in 4x5 = 20 days. Let's assume the total work is 20 units. Efficiency of P = 20/20 = 1 unit/day Efficiency of Q = 20/20 = 1 unit/day Time taken by both of them to finish the whole work when working together = 20/(1+1) = 20/2 = 10 days

      Practice Next
      More Previous year papers Questions
      ask-question