      Question

      The ratio of the amount of work done by (x-1) labours

      in (x+1) days and that done by (x+1) labours in (x+2) days is 5 : 6. Then the value of x is
      A 16 Correct Answer Incorrect Answer
      B 15 Correct Answer Incorrect Answer
      C 17 Correct Answer Incorrect Answer
      D 14 Correct Answer Incorrect Answer

      Solution

      The correct answer is A