Question
P, Q and R together can complete a work in 12 days. All
of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days. Each of the questions below consists of a question and two statements numbered I and II given below it. You have to decide whether the data provided in the statements are sufficient to answer the question. Read both the statements and give answer βSolution
From statement I, it is clear that had P not left the work, the remaining work would have been completed in 6 days. Now since, Pβs efficiency is equal to (Q + R)βs efficiency, now the work will completed in 12 days. Statement II is not related to the question.
Punishment for cheating by personation under Section 319(2) may extend to:
According to the Arbitration and Conciliation Act, which of the following is a ground for challenging the validity of an arbitral award?
As per the Legal Services Authority Act the term case means______________
A limited liability partnership shall, where a person becomes or ceases to be a partner and where there is any change in the name and address of the par...
What is the primary objective of the Minimum Wages Act?
Which of the following Sections of the Companies Act fixes the maximum number of partners in a partnership firm?Β
A Red Herring Prospectus is issued:
Within how many days from incorporation should a company have its first Board meeting?
An internal aid that may be added to include something within a Section or to exclude something from it is known as ___________.
If any loss is caused to the beneficial owner due to the negligence of the depository or the participant.Β