Question

P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together take to complete the remaining work?   I: If P completes a work in X number of days, then Q and R together complete the work in X number of days.   II: After leaving the work, P completed another work in 10 days.

A If the data in statement I alone is sufficient to answer the question, while the data in statement II alone is not sufficient to answer the question. Correct Answer Incorrect Answer
B If the data in statement II alone is sufficient to answer the question, while the data in statement I alone is not sufficient to answer the question. Correct Answer Incorrect Answer
C If the data either in statement I alone or in statement II alone is sufficient to answer the question. Correct Answer Incorrect Answer
D If the data even in both statements I and II together and not sufficient to answer the question. Correct Answer Incorrect Answer
E If the data in both statements I and II together are necessary to answer the question Correct Answer Incorrect Answer

Solution

From statement I, it is clear that had P not left the work, the remaining work would have been completed in 6 days. Now since, P’s efficiency is equal to (Q + R)’s efficiency, now the work will completed in 12 days. Statement II is not related to the question.

Practice Next
×
×