Amit and Bheem can individually
finish a task in 10 days and 15 days, respectively. If they work together to complete the task and earn a total payment of Rs. 600, how much of the payment does Amit receive?Solution
ATQ, Let total task = 30 units {LCM of 10 and 15} Efficiency of 'Amit' = 3 units per day Efficiency of 'Bheem' = 2 units per day Since, they completed the whole task together therefore ratio of wage received by them will be same as the ratio of their efficiencies. So, required wage received by 'Amit' = {3/(3 + 2)} × 600 = Rs. 360
When is National Voters Day observed annually?
Which of the following states was not part of the 'Achievers' category in the LEADS 2024 report for coastal states?
The 'Graphene-Aurora Programme' has been launched recently in collaboration with which ministry?
Who/which among the following has launched the mobile application 'Rajmargyatra'?
Who is the author of the book “Why can’t Elephant be red” ?
Indian Renewable Energy Development Agency has signed an agreement with which bank for financing the projects?
International Nelson Mandela Day is observed on
Who was recently appointed as the Chairperson of the National Medical Commission?
Which government initiative is aimed at promoting financial literacy among school students in India?
Changu dance is a famous folk dance of which of the following states?