Question
The Supreme Court's landmark judgment in Chetan v. The
State of Karnataka established a critical principle regarding circumstantial evidence. The case involved murder allegations where the accused was the last person seen with the victim, and circumstantial evidence was the primary basis for conviction. The Supreme Court held that: Which of the following articulates the principle established in Chetan v. State of Karnataka regarding circumstantial evidence?Solution
In Chetan v. The State of Karnataka, the Supreme Court clarified that the standard for proving a fact (including through circumstantial evidence) under Section 2(j) of the BSA is when "based on reason and evidence, it appears so probable that a prudent person ought, under the circumstances of the particular case, to act upon the supposition that it exists." The judgment reiterated that all circumstances must form a complete chain pointing to guilt beyond reasonable doubt, and no single circumstantial fact alone suffices. This case applies the definition of "proved" under BSA Section 2(j) to circumstantial evidence analysis, establishing that courts must undertake systematic evaluation of the totality of circumstances.
Efficiency of A is 25% more than B and B takes 30 days to complete a piece of work. A started the work alone and then B joined him 4 days before actual ...
Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed t...
Aman, Bishnu, and Chintu can each complete 20%, 25%, and 60% of the work in 4 days, 9 days, and 27 days, respectively. If all thr...
‘A’ and ‘B’ can do a piece of work in 20 days and 32 days, respectively. If they started the work together and worked on it for 5 days, then fin...
A and B are capable of completing a project individually in 40 days and 50 days, respectively. Initially, A and B collaborated on the project, and after...
Ratio of the work done by P, Q and R in one day is 6:4:7 respectively. They all together can complete the work in 45 days. Q and R worked on it for 27 d...
Ram can do a piece of work in 12 days and Shyam can do the same work in 16 days. They both started work together, Ram left 2 days before the completion ...
Efficiency of A, and B are in the ratio of 3 : 4. If both can do a work together in 30 days. Find out how much days A will take to complete the work alone?
P alone can finish a piece of work ‘M’ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ wh...
30 men can complete a work in 12 days. After 9 days, 15 more men joined them. How many days will they now take to complete the remaining work?