    Question

    In the Waterfall model of SDLC, what is the

    characteristic relationship between phases?
    A Phases can overlap significantly and run concurrently. Correct Answer Incorrect Answer
    B Each phase must be completed and approved before the next phase can begin. Correct Answer Incorrect Answer
    C Iterations are short and frequent. Correct Answer Incorrect Answer
    D Requirements are expected to change frequently throughout the project. Correct Answer Incorrect Answer
    E User feedback is continuously integrated into development. Correct Answer Incorrect Answer

    Solution

    Each phase must be completed and approved before the next phase can begin.