The jury for the 2024 Gulbenkian Prize for Humanity was led by former Chancellor Angela Merkel. The prize jury selected the winners from 181 nominations across 117 nationalities. The recognition of the APCNF programme and Dr. Rattan Lal underscores India's leadership in sustainable agricultural practices and climate resilience.
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...
Mike and Jenny alone can complete a task in 24 days and 40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny...
A, B, and C can complete a task individually in 45, 35, and 63 days respectively. They start working together, but A leaves 24 days before the work is c...
35 typists working 9 hours per day can complete a typing job in 14 days. ____ typists working _____ hours per day can complete (3/4)th part of the work ...
- 'Ravi', 'Sohan', and 'Karan' can individually finish a task in 45, 30, and 60 days, respectively. Sohan and Karan work together for ‘x’ days and then l...
If 3 men can finish a task in 4 days, and 4 women can complete the same task in 9 days, how many days will it take for a team of 2 men and 6 women worki...
Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start K...
P and Q can complete a work in 36 days and 54 days, respectively. P, Q and R together can complete the work in 18 days. If R get a total wage of Rs. 594...
A does 4/5 of a piece of work in 20 days. He then calls in B and they finish the remaining work in 3 days. How long B alone will take to do whole work?
A and B together can complete a piece of work in 48 days while B and C together can complete the same work in 58 days. All of three together can complet...