Question
Engineering students who will complete their graduation
this year will find it difficult to get used to the advanced technology being used in the corporate world. Industrial standards are not met with the present infrastructure and quality of teaching in the universities. Hence, continuous upgradation is required. The New Education Policy is a positive step in this direction. However, there is a long way ahead to achieve desired results. I.  There are more engineering students this year that the job openings. II.  The engineering students graduating this year lack the required skills. III.  The infrastructure and teaching faculty currently available is not upto the corporate technological standards. IV.  Engineering students will have to upskill themselves or pursue management education to get better jobs. V.  The New Education Policy may help to meet the gap between the industrial requirements and the universities’ standards. In each of these questions is given a statement followed by assumptions numbered I, II, III etc. An assumption is something supposed or taken for granted. You have to consider the statement and the following assumptions and decide which of the assumption is implicit in the statement. Then select the correct answer from the alternatives.Solution
In the above argument, the premise is that the engineering students this year will find adjusting to the corporate world difficult. On the basis of this premise and some other, the author draws a conclusion about the measures university should take. The author also mentions that New Education Policy can help to achieve those university measures. Assumptions I and IV are not relevant to the statement, as the statement doesn’t talk about jobs or further course of action. Assumption II may be true as the lack of skills may cause adjustment issues to the advanced technology in corporate world. Assumption III is re-iteration of what is mentioned by the author in the statement Assumption V can be true as the author has mentioned that NEP may be a positive step in meeting the gap.
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...