Question
Rohan can finish a certain task in 18 days, whereas Rohan
and Karan together can complete it in 4.5 days. How many days will Karan alone take to complete the task?Solution
ATQ;
Rohan and Karan together take 9/2 days.
Time taken by Karan alone to complete the task =1/[(2/9) - (1/18)] = 1/(4/18) = 18/4 = 9/2
The marked price of an article in two different shops P and Q is Rs 1200 and Rs X respectively. In shop P the article is available at two successive dis...
A watch is sold at a profit of 20%. If both the cost price and selling price are reduced by Rs. 100, then the profit would be 5% more. Find the original...
A shopkeeper first allows a discount of 20% on a certain variety of cloth and then further gives a discount if 15% to the persons holding a shareholder...
- The cost price of an item is Rs. (12n + 240). It is marked 50% above the cost price and sold after giving a discount of Rs. (4n + 80). If the profit earned...
The profit earned by selling an article for Rs. 8,600 is 7/12th the loss incurred on selling the same article for Rs. 5,700. Find the selling price of t...
A shopkeeper give 4 articles free on the purchase of every 12 articles. He also allows a discount of 20% to customer and still earns 20% profit. Find th...
- Rihaan purchased a certain article for Rs. 2600 and then spent some amount on its repair. He marked up the article by 25% above the effective cost price. H...
Rohan bought 50 candies for Rs. 60 and he sold them in such a manner so that selling price of 30 candies is Rs. 54. Find the value of 4(P + 15) if the p...
Ritika purchased a washing machine for Rs. 18,000, listed it 30% above the cost price, and sold it after allowing successive discounts of 10% and 20%. W...
- A vegetable seller buys 12 kg of potatoes at Rs. 40 per kg. While selling, he uses a faulty weight that shows 1250 grams instead of 1000 grams but claims t...