Question
‘Amit’ is 1.5 times as efficient as ‘Bhuvan’, who
is 1/3 as efficient as ‘Chirag’. If Amit and Chirag together complete a work in 18 days, how long will Bhuvan and Dev take to do it if their efficiency ratio is 2:1 respectively?Solution
ATQ,
Let efficiency of Chirag = 3x units/day
Efficiency of Bhuvan = 3x / 3 = x units/day
Efficiency of Amit = 1.5x units/day
Efficiency of Dev = (x / 2) × 1 = 0.5x units/day
Total work = (Amit + Chirag) × 18 = (1.5x + 3x) × 18 = 81x units
Combined efficiency of Bhuvan and Dev = x + 0.5x = 1.5x units/day
Time = 81x / 1.5x = 54 days
'CIBIL Rank' for MSMEs (CIBIL MSME Rank) is provided on a scale of:
What is the 'Margin' in the context of a bank loan?
What initiative was launched by SIDBI in 2018 to track the current state and expected outlook on the MSME sector?
Which organization provides credit insurance to Indian exporters?
What does a 'Zero-Coupon Bond' mean?
Under the Kisan Credit Card (KCC) scheme, the 'Scale of Finance' for a crop is decided by:
Under the prompt corrective action (PCA) framework, which of the following parameters is NOT monitored by the RBI?
What is 'Countercyclical Capital Buffer' (CCyB)?
'Rights Issue' of shares refers to:
As per IRAC (Income Recognition and Asset Classification) norms, an asset is classified as a 'Loss Asset' when: