Question
If 20 men or 12 boys can complete a job in 25 days, how
long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate value)Solution
According to the question,
20M = 12B
Or, 5M = 3B
Therefore, (15M + 18B) = (9B + 18B) = 27B
12 boys take 25 days to complete the work
Therefore, time taken by 27 boys to complete the work = (12 × 25) / 27 = 11.11 days or 11 days
Apple likes to name versions of Mac OS X after big cats. Which cat was version 10.3?
When we say “to boot a computer”, what does it mean?
In the field of computer/IT in open system interconnection on models, there are ____ layers.
 What type of the company is a Google?
What is the name for an application that changes a human-readable programming language into a machine-readable language?
Which high level language is sued for business data processing application?
.__________ is a block of data that can be attached to documents such as PDFs , word processing files, and e-mail messages. It contains a unique cod...
_______ is not related to information technology?
Which of the following is used in second generation computer?
Which of the following is a first Indian web browser?