Question
If 20 men or 12 boys can complete a job in 25 days, how
long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate value)Solution
According to the question,
20M = 12B
Or, 5M = 3B
Therefore, (15M + 18B) = (9B + 18B) = 27B
12 boys take 25 days to complete the work
Therefore, time taken by 27 boys to complete the work = (12 × 25) / 27 = 11.11 days or 11 days
Which Indian company became the third-largest silver producer globally as per the World Silver Survey 2024? Â
Who among the following is best known for his plays 'Yayati' and 'Tughlaq'?
National Income is released by which ministry of central government?
It has been noticed that the frequency of tropical cyclones are more over Arabian Sea and less over Bay of Bengal. What is one of the major reasons f...
Which Article deals with the election of the Vice President?
Which of the following elements is NOT included in the circular flow of Income in a simple economy?
Who among the following is the supreme commander of the Indian armed forces?
Which of the following ministries had launched the Atma Nirbhar Skilled Employee Employer Mapping (ASEEM)’ portal?
As per Census of India 2011, which of the following groups of states recorded the lowest literacy rate?
India ranked 132nd among 191 countries and territories on the 2021 Human Development Index (HDI), which of the following was in the top three?
I....