Start learning 50% faster. Sign in now
Box T is placed in even numbered position. Four boxes are placed between Box X and Box T. Box T is placed above Box X. Only two boxes are placed between the Box Z and Box V in which Box V is placed below Box Z. Box Z is placed in odd numbered position. Box Z is not placed above Box T. From above statements, Case 1: If Box T is placed at 8 th position and then Box X is placed at 3 rd position. Box Z is placed at 7 th position and Box V is placed at 4 th position. Case 1-S: If Box T is placed at 8 th position and then Box X is placed at 3 rd position. Box Z is placed at 5 th position and Box V is placed at 2 nd position. Case 2: If Box T is placed at 6 th position and then Box X is placed at 1 st position. Box Z is placed at 5 th position and Box V is placed at 2 nd position. Based on the above information, we get the initial table as follows Only one box is placed between the Box Y and Box W in which Box W is placed below Box Y. Box X is not placed above Box S. From above statements, Case 1 &2: Based on the above condition, there is no place for Box Y and Box W at s gap of 1 position. Hence, this case becomes invalid and it can be eliminated. Case 1-S: Based on the above condition, Box Y is placed at 6 th position and Box W is 4 th position. Given, Box X is not placed above Box S. Therefore, Box S is placed at 7 th position and Box U is placed at 1 st position. Thus we get the completed table,
Working together, A and B can do a certain work in 45 days. They work together for 10 days. They complete the remaining work in 28 days with the assista...
12 children and 18 men complete an artwork in 9 days. Each child takes twice as long as a man to finish the artwork. How many days will it take for 18 m...
A and B together can complete a piece of work in 48 days while B and C together can complete the same work in 58 days. All of three together can complet...
Anil can do a piece of work in 25 days. He alone worked at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, the...
If 18 men working 18 hours a day can make 18 quilts in 18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?
A and B can complete a task together in 16 days, while B alone takes 32 days to finish it. A began working alone and left after ‘x’ days, after whic...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
With P starting the work, working on alternate days, P and Q can finish a work in 17 days. If Q works on the first day and Q and P work alternately, the...
‘Elvish’ and ‘Farhan’ alone can finish a work in 25 and 50 days, respectively, while ‘Gaurav’ can complete 20% of the job in 10 days. All th...
A, B and C alone can complete a work in 24, 48 and 32 days respectively. All of them started working together but after 2 days from start A left the job...