Question
The question given below consists of some statements
given below it. You have to decide whether the data provided in the statements are sufficient to answer the question. Read all the statements and give answer . Eight persons J, K, L, M, N, O, P and Q sit around a square table in such a way that all are facing towards the center of the table. Four of them sit at the corner of the table while other four sit at the middle of the side of the table. J sits third to the right of L. Two persons sit between J and O. K sits at one of the sides of the table. Who sits second to the left of N? Statement I: Two persons sit between K and N, who doesn’t sit adjacent to L. P sits immediate left of N. Statement II: P sits second to the right of Q, who sits exactly between L and O. Q doesn’t sit at the corner. N doesn’t sit adjacent to K.Solution
From statement I and given statement, we get Case 1: When J sits at the corner. Â Case 2: When J sits at the middle of the side.
Either J or L sits second to the left of N. So, statement I alone is not sufficient to answer the question. From statement II and given statement, we get
L sits second to the left of N. So, statement II alone is sufficient to answer the question.
Ravi and Sunil can complete a task in 12 days and 30 days respectively. Ravi started the task alone. After how many days should Sunil join him so that t...
‘A’ can do 30% of the work in 12 days. ‘B’ can do the whole work in 50 days. Find the time taken by them together to do 75% of the work.
...Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.
A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C ...
Some Category of workers can complete a decided project in 20 days. However, due to some unpredicted situation, 5 workers were absent. That’s why, the...
A team leader can do a job as fast as three members of the team working together. If one of the members can do the job in 5 hrs, the second one takes 10...
A does 55% of some work in 12 days. Later, with B’s help, she completes the remaining work in 4 days. In how many days can Be B complete the entire wo...
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days w...
Pawan can finish a task in 28 days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started wor...
Pipe A alone can fill 75% of a cistern in 18 minutes. When both Pipe A and Pipe B are opened together, they can fill the entire cistern in 33 minutes. H...