Chef X, Chef Y, and Chef Z can prepare 22 dishes individually in 5 hours, 10 hours, and 15 hours respectively. For the presidential brunch, they agreed upon 22 dishes that they would prepare together. All three chefs started cooking at 8 am, but due to some personal emergency, Chef Y had to leave at 10 am. At what time would the brunch be ready?
Solution
Fraction of the dishes prepared by Chef X in 1 hour = 1/5 Fraction of the dishes prepared by Chef Y in 1 hour = 1/10 Fraction of the dishes prepared by Chef Z in 1 hour = 1/15 β΄ Fraction of the dishes prepared by all three chefs in 1 hour = 1/5 + 1/10 + 1/15 = 11/30 Also, Fraction of dishes prepared by Chef X and Chef Z in hour = 1/5 + 1/15 = 4/15 From 8 am to 10 am, all the Chefs were working. They all worked for 2 hours. β Fraction of the dishes prepared = 2 * 11/30 = 11/15 β΄ Pending fraction of dishes = 1 - 11/15 = 4/15 β΄ Time taken by Chef X and Chef Z to prepare the remaining dishes = (4/15)/(4/15) = 1 hour = 60 min. β The brunch will be ready at 11:00 am. Β
- A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively. If B works daily and is supported by A and C on alternate days beginning wi...
- A and B can do job in 10 days. B and C can do same job in 12 days. A, B and C together can do same job in 8 days. In how many days A and C together can com...
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- Pipes A and B can fill an empty tank in 6 and 8 hours respectively, while pipe C can empty the full tank in 10 hours. If all three pipes are opened togethe...
- Sanjay and Amit can do a piece of work in 8 days. Amit alone can do it in 12 days. In how many days will Sanjay do it alone?
- A can do a piece of work in 15 days while B can do it in 18 days. Starting with A, they work on alternate days till the work gets over. How many days in al...
- A and B can do a certain work in 6 hours, and A, B and C together take 4 hours to do the same. How long will it take for C alone to accomplish the task?
- Question 9
- Working alone, B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working toget...