πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A, B and C can individually complete a piece of work in

      24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work, is:
      A 11 Correct Answer Incorrect Answer
      B 15(1/2) Correct Answer Incorrect Answer
      C 18 Correct Answer Incorrect Answer
      D 13(1/5) Correct Answer Incorrect Answer

      Solution

      Let the total work be 120 units. (LCM of 24, 15 and 12 is 120.) Efficiency of A = work/time = 120/24 = 5 units/day Efficiency of B = 120/15 = 8 units/day Efficiency of C = 120/12 = 10 units/day Work done by B and C in 3 days = (8 + 10) 3 = 54 units Remaining work = 120 - 54 = 66 units Time taken by A to complete the remaining work = 66/5 = 13(1/5)

      Practice Next

      Relevant for Exams:

      ask-question