28 men and 21 women can complete the work in 16 days. ∴ Work done by them in 12 days = 12/16 = 3/4 Remaining 1-3/4 = ¼ work is completed by 28 men in 8 days. => Time taken by only 28 men to complete the whole work = 4 x 8 = 32 days. Work done by 21 women in a day = 1/16 – 1/32 = 1/32 ∴ Time taken by 21 women to complete the work = 32 days