πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      β€˜A’ can complete 2/5 of a work in 6 days. β€˜B’

      takes 9 days more than β€˜A’ to complete the work and B is 25% more efficient than β€˜C’. β€˜A’ started the work alone and on 2nd day, he is joined by β€˜B’ only, on 3rd day, he is joined by β€˜C’ only and on 4th day, he works alone again and so on. They worked this way for 9 days. The sum of the time taken to complete the remaining work by β€˜A’ alone and by β€˜B’ alone is how much percent more/less than that by β€˜C’ alone?
      A 20% Correct Answer Incorrect Answer
      B 30% Correct Answer Incorrect Answer
      C 50% Correct Answer Incorrect Answer
      D 80% Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, A completes 2/5 of work in 6 days. Time for whole work = 6 Γ· (2/5) = 6 Γ— 5/2 = 15 days. B’s time = 15 + 9 = 24 days. B 25% more efficient than C β‡’ C’s time = 24 Γ— 5/4 = 30 days. Let total work = 600 units. A’s efficiency = 600/15 = 40 units/day. B’s efficiency = 600/24 = 25 units/day. C’s efficiency = 600/30 = 20 units/day. Work in 3-day cycle: 40 + 65 + 60 = 165 units. In 9 days: 165 Γ— 3 = 495 units. Remaining = 600 βˆ’ 495 = 105 units. Time by A = 105/40 = 21/8 days. Time by B = 105/25 = 21/5 days. Time by C = 105/20 = 21/4 days. Sum(A+B) = 273/40 days. Excess over C = 273/40 βˆ’ 21/4 = 63/40 days. Required percentage = (63/40 Γ· 21/4) Γ— 100 = 30% more.

      Practice Next
      ask-question