πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    β€˜A’ is 50% more efficient than β€˜B’. β€˜A’ and

    β€˜B’ work together for 6 days after which β€˜A’ is replaced by β€˜C’. β€˜B’ and β€˜C’ together take 6 more days to finish the work. If β€˜A’ alone could’ve finished the whole work in 20 days, then find the time taken by β€˜C’ to finish 50% work alone.
    A 8 days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer
    E 10 days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x Γ— 1.5 = '1.5x' units/day Total work = 20 Γ— 1.5x = '30x' units So, work done by 'A' and 'B' together in 6 days = (x + 1.5x) Γ— 6 = '15x' units So, remaining work = 30x - 15x = '15x' units So, efficiency of 'B' and 'C' together = 15x Γ· 6 = '2.5x' units per day So, efficiency of 'C' = 2.5x - x = '1.5x' units/day So, required time = (30x Γ— 0.5) Γ· 1.5x = 10 days

    Practice Next

    Relevant for Exams:

    ask-question