πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      'A' and 'B' together can do a piece of work in 15 days

      while 'B' and 'C' together can do the same work in 12 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 8 days and 'C' alone completed the remaining work in 14 days. Find the time taken by 'B' alone to complete the whole work.
      A 50 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 60 days Correct Answer Incorrect Answer
      D 40 days Correct Answer Incorrect Answer
      E 45 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 60 units. {LCM of 15 and 12} Combined efficiency of 'A' and 'B' = 60 Γ· 15 = 4 units/day Combined efficiency of 'B' and 'C' = 60 Γ· 12 = 5 units/day Work by A in 1 day = a units
      Work by B in 8 days = 8b units
      Work by C in 14 days = 14c units a + b = 4
      b + c = 5 So, a = 4 βˆ’ b and c = 5 βˆ’ b (4 βˆ’ b) + 8b + 14(5 βˆ’ b) = 60
      4 βˆ’ b + 8b + 70 βˆ’ 14b = 60
      74 βˆ’ 7b = 60
      7b = 14
      b = 2 units/day Time taken by 'B' alone = 60 Γ· 2 = 30 days

      Practice Next

      Relevant for Exams:

      ask-question