πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      'A' and 'B' together can do a piece of work in 12 days

      while 'B' and 'C' together can do the same work in 15 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 8 days and 'C' alone completed the remaining work in 16 days. Find the time taken by 'B' alone to complete the whole work.
      A 60 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 45 days Correct Answer Incorrect Answer
      D 48 days Correct Answer Incorrect Answer
      E 36 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 60 units. {LCM of 12 and 15} Combined efficiency of 'A' and 'B' = 60 Γ· 12 = 5 units/day Combined efficiency of 'B' and 'C' = 60 Γ· 15 = 4 units/day Amount of work done by 'A' in 1 day = 1 Γ— a units
      Amount of work done by 'B' in 8 days = 8 Γ— b units
      Amount of work done by 'C' in 16 days = 16 Γ— c units We have,
      a + b = 5
      b + c = 4 From these, a = 5 βˆ’ b and c = 4 βˆ’ b Total work done = 60 units
      So,
      1(5 βˆ’ b) + 8b + 16(4 βˆ’ b) = 60
      5 βˆ’ b + 8b + 64 βˆ’ 16b = 60
      69 βˆ’ 9b = 60
      9b = 9
      b = 1 unit/day Time taken by 'B' alone to complete the work = 60 Γ· 1 = 60 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question