📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    'A' and 'B' together can do a piece of work in 12 days

    while 'B' and 'C' together can do the same work in 15 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 8 days and 'C' alone completed the remaining work in 16 days. Find the time taken by 'B' alone to complete the whole work.
    A 60 days Correct Answer Incorrect Answer
    B 30 days Correct Answer Incorrect Answer
    C 45 days Correct Answer Incorrect Answer
    D 48 days Correct Answer Incorrect Answer
    E 36 days Correct Answer Incorrect Answer

    Solution

    Let the total work be 60 units. {LCM of 12 and 15} Combined efficiency of 'A' and 'B' = 60 ÷ 12 = 5 units/day Combined efficiency of 'B' and 'C' = 60 ÷ 15 = 4 units/day Amount of work done by 'A' in 1 day = 1 × a units
    Amount of work done by 'B' in 8 days = 8 × b units
    Amount of work done by 'C' in 16 days = 16 × c units We have,
    a + b = 5
    b + c = 4 From these, a = 5 − b and c = 4 − b Total work done = 60 units
    So,
    1(5 − b) + 8b + 16(4 − b) = 60
    5 − b + 8b + 64 − 16b = 60
    69 − 9b = 60
    9b = 9
    b = 1 unit/day Time taken by 'B' alone to complete the work = 60 ÷ 1 = 60 days

    Practice Next

    Relevant for Exams:

    ask-question