Question
'A' and 'B' together can do a piece of work in 12 days
while 'B' and 'C' together can do the same work in 15 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 8 days and 'C' alone completed the remaining work in 16 days. Find the time taken by 'B' alone to complete the whole work.Solution
Let the total work be 60 units. {LCM of 12 and 15} Combined efficiency of 'A' and 'B' = 60 Γ· 12 = 5 units/day Combined efficiency of 'B' and 'C' = 60 Γ· 15 = 4 units/day Amount of work done by 'A' in 1 day = 1 Γ a units
Amount of work done by 'B' in 8 days = 8 Γ b units
Amount of work done by 'C' in 16 days = 16 Γ c units We have,
a + b = 5
b + c = 4 From these, a = 5 β b and c = 4 β b Total work done = 60 units
So,
1(5 β b) + 8b + 16(4 β b) = 60
5 β b + 8b + 64 β 16b = 60
69 β 9b = 60
9b = 9
b = 1 unit/day Time taken by 'B' alone to complete the work = 60 Γ· 1 = 60 days
What should come in place of (?) question mark in the given expression.
(576 Γ· 12) + (3Β³ Γ 4) = ?
- 60% of 180 β 30% of 60 = 15% of ?
What will come in the place of question mark (?) in the given expression?
(252 + 198) Γ· ? + 126 Γ· 3 = 144 Γ· 2
- Find the simplified value of following expression:
0.998 + 0.882 + 0.12 β529 + β64 + 92 = ?
What will come in the place of question mark (?) in the given expression?
? = (20 Γ 62 β 342 )
What will come in the place of question mark (?) in the given expression?
(β1024 + β324)% of 780 = ?% of 260
15848 Γ· 4 β 793 Γ 6 + 3628 = 3 Γ ?
{(5/8) + (4/5)} Γ (?/19) = 33