Question
Karan is capable of doing 50% of a job in 25 days, while
Meera does 25% of it in 20 days. Karan works for 20 days and then leaves. How many days will Meera take to complete the remaining task?Solution
ATQ,
Karan’s full-time = 25 / 0.50 = 50 days
Meera’s full-time = 20 / 0.25 = 80 days
Total work = LCM(50, 80) = 400 units
Karan’s efficiency = 400 / 50 = 8 units/day
Meera’s efficiency = 400 / 80 = 5 units/day
Work done by Karan = 20 × 8 = 160 units
Remaining work = 400 - 160 = 240 units
Time by Meera = 240 / 5 = 48 days
Which of the following is not an example of a popular web-based search engine?Â
Pokemon Go uses which of the following ?
__________ are attempts by individuals to obtain confidential information from you by falsifying their identity.
What is a DDoS (Distributed Denial of Service) attack in networking?
________________ is a method by which instruction execution speed is improved by putting the steps into parallel.
In networking, what does 'IP' stand for?
Which of the following hardware can provide Firewall security?
To delete the selected item permanently, which of the following shortcut key combination should be used?
What is the number of function keys on a keyboard?
Which of the following is NOT a layer of the Internet Protocol Suite (TCP/IP)?