      Karan is capable of doing 50% of a job in 25 days, while

      Meera does 25% of it in 20 days. Karan works for 20 days and then leaves. How many days will Meera take to complete the remaining task?
      A 48 days Correct Answer Incorrect Answer
      B 61 days Correct Answer Incorrect Answer
      C 52 days Correct Answer Incorrect Answer
      D 35 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Karan’s full-time = 25 / 0.50 = 50 days

      Meera’s full-time = 20 / 0.25 = 80 days

      Total work = LCM(50, 80) = 400 units

      Karan’s efficiency = 400 / 50 = 8 units/day

      Meera’s efficiency = 400 / 80 = 5 units/day

      Work done by Karan = 20 × 8 = 160 units

      Remaining work = 400 - 160 = 240 units

      Time by Meera = 240 / 5 = 48 days