Karan is capable of doing 50% of a job in 25 days, while
Meera does 25% of it in 20 days. Karan works for 20 days and then leaves. How many days will Meera take to complete the remaining task?Solution
ATQ,
Karan’s full-time = 25 / 0.50 = 50 days
Meera’s full-time = 20 / 0.25 = 80 days
Total work = LCM(50, 80) = 400 units
Karan’s efficiency = 400 / 50 = 8 units/day
Meera’s efficiency = 400 / 80 = 5 units/day
Work done by Karan = 20 Ă— 8 = 160 units
Remaining work = 400 - 160 = 240 units
Time by Meera = 240 / 5 = 48 days
Match List I with List II :
Choose the correct answer...
pF value of hygroscopic coefficient isÂ
Which stage of the product life cycle causes the profit to improve substantially?
In the soil water-plant continuum, what is the driving force that allows water to move from the soil through the plant to the atmosphere?
Microbodies associated with mitochondria and chloroplasts containing the enzyme glycolate oxidase are known as
In India, every year the National Farmers  Day is celebrated on:
How many ATP are formed in the Krebs cycle from citric acid to alpha-ketoglutaric acid?
Given below are wo statements, one is labelled as Assertion A and the other is labelled as Reason R
Assertion A: The probe of a neutron moisture ...
If a plant or plant organ such as root is supplied with low oxygen concentrations in a water logged or compacted soil, anaerobic respiration takes place...
The symbiotic association ,Mycorrhizae help in absorption of: