Question
Pawan completes 40% of a task in 6 days. His efficiency
is 100% greater than Qureshi's. How many days will it take for both Pawan and Qureshi, working together, to finish the entire task?Solution
ATQ,
Pawan’ alone can do the complete work in (6/0.4) = 15 days
Efficiency of ‘Pawan’ = 2 × efficiency of ‘Qureshi’
As, we know efficiency is inversely proportional to time taken when work done is constant.
So, ‘Qureshi’ alone can complete the work = (15 × 2) = 30 days
Let the total work be 30 units {LCM of 15 and 30}
Efficiency of ‘Pawan’ = (30/15) = 2 units/day
Efficiency of ‘Qureshi’ = (30/30) = 1 unit/day
So, time taken by ‘Pawan’ and ‘Qureshi’ to complete the work together = (30/3) = 10 days
Falsus in uno falsus in omnibus i.e. false in one thing, false in everything, the said maxim is _______.
Under the Bharatiya Sakshya Adhiniyam, 2023, what does the term "proved" mean?
A person shall be deemed to be dead if he remained unheard for_______years.Â
Milk is adulterated with:
Provision for award of cost is provided in which of the following Sections of Code of Civil Procedure?
Certificate for appeal to the Supreme Court is made by High Court as per ______ of the Indian Constitution.
As per the provisions of the Companies Act One Person Company shall have minimum ______________ director
Who are the persons who are not eligible to make an application for the initiation of the corporate insolvency resolution process under the IBC?
The fee payable to the experts appointed by the Court as per section 14A of the Specific Relief Act shall _____________
What powers does the Supreme Court have concerning the enforcement of rights conferred by Part III of the Constitution?