A and B can complete a task together in 30 days, while B alone takes 60 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 45 days. Determine the percentage of the total work completed by
A and B can complete a task together in 30 days, while B alone takes 60 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 45 days. Determine the percentage of the total work completed by
A.
More Approximation Questions
- 85.22 of 499.98% + 299.99 ÷ 30.18 = ?
- (98.03 + 186.98) ÷ 19.211 = 89.9 – 20.23% of ?
- What approximate value will come in place of the question mark (?) in the following question? 37.62% of 2499.84 – 438.27 = ? × 20.11
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.) ...
- 14.742 ÷ 24.98 × 15.76 = ?% of 359.88
- (2520.33 ÷ 41.67) × (√168.88 + √80.78) - 10% of 1499.85 = ?
- What approximate value should come in the place of (?) in the expression given below? √2401.04 - √1370 - √3720.96 =?
- (115.25 + 324.78) ÷ 4.99 = ?2 – 56.44
- Question 9
- What approximate value will replace the question mark (?) in the following? 29.99% of 540.1 = 19.89% of ?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)