Question
Anoop and Bheema, working
individually, can complete a task in 16 days and 12 days, respectively. If they worked together and earned a total wage of Rs. 4,900, what is Anoop's share of the total wage?Solution
ATQ, Since, 'Anoop' and 'Bheema' completed the work together therefore ratio of the wages received by them will be same as the ratio of their efficiencies. Ratio of efficiencies is reciprocal of the ratio of the time taken by them Therefore, ratio of efficiency of 'A' to that of 'B' = (1/16) :(1/12) = 12:16 = 3:4 Therefore, wage received by 'Anoop' = 4900 × (3/7) = Rs. 2,100
In which year the Kheda Satyagraha was started in India?
What is India’s first solar mission, launched in 2022?
Who became the Chief Minister of Gujarat in September 2024?
Who has been elected as the new Chief Minister of Chhattisgarh as of (2025)?
The 36th National Junior Athletics Championship was held in _______ from February 6 to February 10, 2021.
 Indian Fundamental Rights have been taken from which of the following countries?
The scientific name of Tomato is_____