Question
"A" and "B" together can complete a task in 16 days.
Additionally, "B" alone is able to complete 40% of the task in 16 days. Based on this information, calculate the time it would take for "A" to complete 60% of the task on their ownSolution
Time taken by 'B' to do 100% of the work alone = 16 ÷ 0.4 = 40 days Let total work be 80 units {LCM (40 and 16)} So, efficiency of 'B' = 80 ÷ 40 = 2 units/day And efficiency of 'A' and 'B' together = 80 ÷ 16 = 5 units/day So, efficiency of 'A' = 5 - 2 = 3 units/day So, required time = 80 X 0.6 ÷ 3 = 16 days
Under which of the following Market Competition, Production is at socially ideal level?
As per the Economic Survey 2016-17, the expected range of GDP growth (at constant price) for the year 2017-18 is between?
The monetary policy is India is formulated by which of the following authority?
Which committee recommended the establishment of Regional Rural Banks in India?
What is the main objective of the SHRESHTA Scheme?
Which of the following is not part of the World Bank Group of Institutions?
Consumer sovereignty implies that consumers:Â
Market of government securities is also known as
Philips Curve is a graphic curve advocating a relationship between which factors?
What does 'VAT' stand for in the context of taxation?