Question
'A' can complete a project in 15 days but worked only
the first 4 days. 'B', who is 80% as efficient as 'A', takes over. How long does 'B' need to finish the remaining work?Solution
Let the efficiency of 'A' be 'x' units/day So, efficiency of 'B' = '0.8x' units/day Total work = x X 15 = '15x' units Work done by 'A' in 4 days = 4 X x = '4x' units So, remaining work = 15x - 4x = '11x' units So, time taken by 'B' to finish the remaining work = (11x ÷ 0.8x) = 13(3/4) days
A. And taking this village lad into their midst was terribly upsetting.
B. She was by no means pleased with this unnecessary addition to her fami...
Choose the correct order.
1. Kevin was eagerly waiting for his holidays.
P. His mother kept on hinting there would be a big surprise ...
Parts of a sentence are given below in jumbled order. Arrange the parts in the right order to form a meaningful sentence
A. to lift 8 million peo...
In the question given below, some sentences/phrases are given which have to be arranged in a proper sequence. Select the option that best defines the p...
Sentences of a paragraph are given in jumbled order. The first and last sentences (S1 and S6) are given. Arrange the sentences in the correct order to f...
The furniture in the living room (1)/ need to be rearranged (2)/ because the space looks (3)/ too cluttered. (4)/ No error (5)
Given below are six sentences, out of which sentences A and F are in the correct position. Sentences B, C, D and E are in a jumbled order. Select the op...
Which of the following is the second sentence of the passage?              Â
Given below are a few sentences in which four words are emboldened each. The words may or may not be in their correct position. Rearrange the words if ...
In the question given below, some sentences/phrases are given which have to be arranged in a proper sequence. Select the option that best defines the p...