Question
14 women working 8 hours a day
can complete a piece of work in 30 days. What is the time taken by 28 men working 5 hours a day to complete the work if the efficiency of a woman is 30% less than that of a man?Solution
ATQ,
Let the efficiency of a man be '5a' units/day. So, the efficiency of a woman = 0.70 × 5 = '3.5a' units/day. Total work = 14 × 3.5a × 8 × 30 = '11760a' units. So, time taken by 28 men working 5 hours a day to complete the work: = 11760a ÷ (28 × 5a × 5) = 16.8 days.
More Alligation Questions
- Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___