Question

14 women working 8 hours a day can complete a piece of work in 30 days. What is the time taken by 28 men working 5 hours a day to complete the work if the efficiency of a woman is 30% less than that of a man?

A 25.5 days
B 12.8 days
C 16.8 days
D 22.5 days