Question
If 6 men and 5 boys can complete a piece of work in 9
days, while 24 men and 20 boys can complete the same work in 3 days, how long will it take for 12 men and 15 boys to complete the same work?Solution
Let the efficiency of a man be βpβ units per day and the efficiency of a boy be βqβ units per day. According to the question: (6p + 5q) Γ 9 = (24p + 20q) Γ 3 Or, 54p + 45q = 72p + 60q Or, 15q = 18p Or, q = 1.2p Total work = (6p + 5q) Γ 9 = (6p + 6p) Γ 9 = 12p Γ 9 = β108pβ units Efficiency of 12 men and 15 boys = 12p + 15q = 12p + 18p = 30p units per day Required time = (108p / 30p) = 3.6 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?