Question
A can complete 15% of the work in 20% of the allotted
time. A and B worked for the entire period of the allotted time and the work was completed on time. What portion of the work was done by B?Solution
Let the total time taken by them be 100 minutes. So, Â 20% of 100 minutes = 20 minutes Now, 15% of work is completed in 20 minutes by A 3% of work is completed in 4Â minutes by A 75% of work is completed in 100Â minutes by A If A can complete 75% in 100 minutes, then, B will complete the remaining portion i.e. (100 - 75) = 25% Â 25% of the work was done by B.
In Excel typical worksheet has …. Number of columns
A half byte is know is
While studying about computer, we may came to know about the term QDR. Expand QDR?
A saved document is referred to as _________.
Word processing, spreadsheet, and photo-editing are examples of which type of software?
To print a document which shortcut is used?
Which of the following is a form of malware that encrypts a victim's files?
Which of the following Internet protocol specifies how data is exchanged over the Internet and how it should be broken into IP packets?
What happens when you press the "Insert" key on the keyboard?
Which sorting algorithm has a worst-case time complexity of O(n²)?