Question
βAβ alone can complete a work in 12 days. βBβ
alone can complete the same work in 24 days. If βAβ and βBβ work together for 4 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 24 units {LCM of 12 and 24} Then, efficiency of βAβ = 24/12 = 2 units/day Efficiency of βBβ = 24/24 = 1 units/day Combined efficiency of βAβ and βBβ = 2 + 1 = 3 units/day Work completed by βAβ and βBβ together in 4 days = 3 Γ 4 = 12 units Remaining work = 24 β 12 = 12 units Time taken by βAβ alone to complete the remaining work = 12/2 = 6 days
The South Korean won is the official currency of which country?
What percentage of deposits were held by individuals as of September 2024, according to the RBI Quarterly BSR-2 report?
Consider the following statements about βWarli paintingβ:Β
1.Β Β Β Recently, an exhibition traces the artistic journey of the Mashe family ...
How many AI start-ups are expected to benefit from NVIDIAβs Inception Program under the AP initiative?
Who has been appointed as the new Economic Affairs Secretary effective July 1, 2025?Β
What amount did LIC pay as stipend to Bima Sakhis in FY2024β25?
Which of the following startup of India became 100th unicorn startup?
Who became the second Indian woman to win a gold medal at the World Military Championships?
What is the main purpose of the Deregulation Commission announced by the Indian government?
Where in India the Kisan Bhawan and Beekeepers Conference has been inaugurated?