Question
βAβ alone can complete a work in 12 days. βBβ
alone can complete the same work in 24 days. If βAβ and βBβ work together for 4 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 24 units {LCM of 12 and 24} Then, efficiency of βAβ = 24/12 = 2 units/day Efficiency of βBβ = 24/24 = 1 units/day Combined efficiency of βAβ and βBβ = 2 + 1 = 3 units/day Work completed by βAβ and βBβ together in 4 days = 3 Γ 4 = 12 units Remaining work = 24 β 12 = 12 units Time taken by βAβ alone to complete the remaining work = 12/2 = 6 days
At the Paris Summer Olympics, in which event did Swapnil Kusale win his first Olympic bronze medal?
Which Indian state recently celebrated its 56th liberation day to commemorate its independence from Portugese rule
____________ Line is the boundary dividing Germany and Poland
In which of the following state Nag River flow?
Which of the following countries is not a member of the SAARC (South Asian Association for Regional Cooperation).
In ancient times, what was Awadh (Oudh) known as?
Who was the brand ambassador of Thums Up in 2022?
May 29th is observed as the
Which village in Maharashtra was the first to be fully powered by solar energy under the Solar Village Scheme?
Of which of the following who was the first ever industrialist to get the Bharat Ratna?