‘A’ and ‘B’ can do a piece of work in 10 days and 15 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B’ to complete the remaining work.
More Time and work Questions
- ‘D’ can type a document in 45 days, but ‘D’ and ‘E’ together can do it in 27 days. If ‘E’ worked for 15 days alone and then left, in how many days will ‘D’...
- ‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then fin...
- Two pipes X and Z can fill a tank in 36 hours and 48 hours respectively, while pipe Y can drain the tank in 72 hours. If pipes X and Z are opened together ...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
- 'B' can complete a task in 15 days, and when 'A' and 'B' collaborate, they can finish the same task in 8 days. 'A' initiated the work alone and worked for ...
- 16 men can complete a work in 10 days. 10 men started the same work and left after working for ‘y’ days. The remaining work is completed by 6 men in 15 day...
- The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by...
- A, B, and C are three workers who can complete a certain piece of work. A alone can complete the work in 12 days. B alone can complete the same work in 3X ...
- P’s 5 days work is equal to Q’s 7 days work. If P and Q together can complete the work in 20 days then how much time Q will take to complete 75% of the wor...
- If 20 men or 12 boys can complete a job in 25 days, how long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate...