Question
βAβ and βBβ can do a piece of work in 10 days
and 15 days, respectively. They started working together but βAβ left after 3 days. Find the time taken by βBβ to complete the remaining work.Solution
Let total amount of work be 30 units (LCM of 10 and 15). Efficiency of βAβ = 30/10 = 3 units/day Efficiency of βBβ = 30/15 = 2 units/day Amount of work done by βAβ and βBβ together in 3 days = (3 + 2) Γ 3 = 15 units Time taken by B to complete remaining work = {(30 β 15)/2} = 7.5 days
The sum of the digits of a two-digit number is 9, and when the digits are reversed, the number decreases by 45. Find the changed number.
Find the number of multiplication blocks in 52900.
In a four digit number, the units place digit is one more than the hundreds place digit and the tens place digit is one less than the thousand place dig...
Divisor is 7 times of Quotient and 3 times of its remainder. If the remainder is 7. Find the dividend?
Find the difference between minimum and maximum value of 'k' such that '6k8194' is always divisible by 3.
- When 5 1850 Β is divided by 126, the remainder is:
- If '48x2y' is a five-digit number which is divisible by 72, then find the value of (x - y).
- 40% of 30% of 750 = x + 15, then find the sum of the squares of the digits of 'x'.
- Determine the total sum of all three-digit numbers that are divisible by both 2 and 7.
Two friends received a bonus of βΉ3,000 each in their bank accounts. They already have βΉ47,000 and βΉ57,000 in their respective bank accounts. The r...