📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      ‘A’ and ‘B’ can do a piece of work in 20 days

      and 25 days, respectively. If they started the work together and worked on it for 4 days, then find the time taken by ‘B’ alone to complete the remaining work.
      A 10 days Correct Answer Incorrect Answer
      B 11 days Correct Answer Incorrect Answer
      C 16 days Correct Answer Incorrect Answer
      D 13 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 100 units  Efficiency of ‘A’ = 100/20 = 5 units/day Efficiency of ‘B’ = 100/25 = 4 units/day Amount of work done by ‘A’ and ‘B’ together in 4 days = (5 + 4) × 4 = 36 units Time taken by B to complete remaining work = (100 – 36)/4 = 16 days

      Practice Next

      Relevant for Exams:

      ask-question