Question
Akhil and Nikhil together can complete a work in 12 days
while Nikhil alone takes 18 days to complete 30% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 18/0.30 = 60 days Let the total work = 60 units Efficiency of (Akhil + Nikhil) = 60/12 = 5 units/day Efficiency of Nikhil = 60/60 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 60/5 = 12 days
For the offence of abduction of person, abducted must be:Â
Under Negotiable Instrument Act 1881, a negotiable instrument may be negotiatedÂ
According to the Arbitration and Conciliation Act which of the following is incorrect with respect to an Arbitration Agreement?
An injunction can be granted:
In the context of insurance policies, who does the term "policy-holder" include as per the Insurance Act?
The Advertisement of a Prospectus of a company shall specify therein the _____________
Which of the following section of CPC gives inherent power to civil court?
Extreme old age when a man behaves like a child is called :
In the context of electronic or digital records, when a record is stored in multiple storage spaces in a computer resource, how is each automated storag...
Who has the power to decide on the rules of qualification of National Commission President?