Question

Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 30% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.

A 12 days Correct Answer Incorrect Answer
B 10 days Correct Answer Incorrect Answer
C 20 days Correct Answer Incorrect Answer
D 15 days Correct Answer Incorrect Answer

Solution

Time taken by Nikhil to complete the whole work alone = 18/0.30 = 60 days Let the total work = 60 units Efficiency of (Akhil + Nikhil) = 60/12 = 5 units/day Efficiency of Nikhil = 60/60 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 60/5 = 12 days