Question
Akhil and Nikhil together can complete a work in 12 days
while Nikhil alone takes 18 days to complete 30% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 18/0.30 = 60 days Let the total work = 60 units Efficiency of (Akhil + Nikhil) = 60/12 = 5 units/day Efficiency of Nikhil = 60/60 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 60/5 = 12 days
Dada Saheb Phalke Award is given for outstanding contribution in the field of
Who are the eligible beneficiaries of Abua Awas Yojna ?
A) Homeless or unattended individuals.
B) Particularly Vulnerable Tribal Group (PV...
In which district of Rajasthan the fair of Sitabari is organised?
What disease in cattle is caused by the bacterium Mycobacterium bovis?
Article 280 of the Constitution is related to which of the following?
What is the upper limit of a single UPI transaction for merchant payments as per NPCI (2024)?
In the list of 100 Most Powerful Women Forbes 2020 the finance minister Nirmala Sitharaman secured the position at?
In ________ Guru Gobind Singh convened a general meeting of the Sikhs ar Anandpur Sahib on Baisakhi day and laid the foundation of Khalsa (or the pure).
What is the full form HAM?
Consider the following statements:
Statement I:
The Government of India mandates the packaging of 100% sugar and food grains in diver...