Question
A, B, and C together can do a work alone in 12 days, 18 days, and 54 days respectively. A alone starts the work and work for 3 days and leaves the work, then B alone does the work for 8 days and leaves the work. If remaining work is done by C alone then for how many days has C worked?
More Quant Miscellaneous Questions
- If log₃(x + 1) − log₃(x − 1) = 2, find x.
- If the sales of Product C increase by 50% and the sales of Product D decrease by 20%, what will be the new total sales of all products combined?
- Question 3
- A sum of Rs. 55,000 becomes Rs. 72,600 after 2 years when invested at simple interest at r% per annum. What will be the simple interest earned on Rs. 80,00...
- What will be come in place of (?) in the given number series. 7, 11, 15, 19, ?, 27
- Find the value of 24 - 3 (correct to 3 decimal places).
- The speed of boat 'Y' in still water is the same as the downstream speed of boat 'X'. Boat 'X' requires 1 hour longer than boat 'Y' to travel 80 km downstr...
- Question 8
- If 5 sin x - 12 cos x = 0, find the value of tan x.
- If the volume of a solid hemisphere is 155232cm³ then find the diameter of the solid hemisphere.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)