Let the total work be LCM of (16, 24 and 8) = 48 units Number of units of work done by P alone in one day = 48/16 = 3 units Number of units of work done by Q alone in one day = 48/24 = 2 units Number of units of work done by P, Q and R together in one day = 48/8 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 48/1 = 48 days So, per day wage of R = 3360/48 = Rs. 70
Which of the following crop is usually grown in zaid season in Uttar Pradesh?
Semi – conservative mode of DNA replication was proved by
Which one of the following is a physical method of weed control?
During 2020-21 NAFED did what under Price Support Scheme?
Sunflower is the indicator plant of which nutrient deficiency in soil?
In dryland regions, which of the following cropping systems is most appropriate for conserving soil moisture and reducing the risk of total crop failure?
Irrigation water safely used for irrigation purpose have SAR value
Black heart, a physiological disorder, is associated with which crop?
Charcoal Rot of Soybean is caused by: