Question
P alone can finish a piece of work βMβ in 9 days
while Q takes 3 days to finish it alone. P, Q and R working together can finish the work βNβ which is 12 times of work βMβ in 9 days. How long will R take to finish work βNβ, when working alone?Solution
Β Let the work βMβ = 9 units (LCM of 9 and 3) Efficiency of P = 9/9 = 1 units Efficiency of Q = 9/3 = 3 units Efficiency of P, Q and R = (9 Γ 12)/9 = 12 units per day Efficiency of R = 12 β (1 + 3) = 8 units per day Time taken by R to finish work βNβ = 108/8 = 13.5 days
According to the WMO, what concentration of CO β was recorded in 2023, representing 151% of pre-industrial levels?
Sh Ajay Kumar Chaudhary who is appointed as a new Executive Director of RBI, was earlier designated as:
What is the total financial outlay of the BHAVYA Scheme?
The AgriSURE fund aims to support high-risk ventures in which sector?
What is the effective import duty on edible oils after the recent government revision?
What is the significance of the heritage train flagged off by Prime Minister Narendra Modi in Gujarat?Β
___________ topped the World's Best Employers 2021 rankings released by Forbes.
Recently Dmitry Muratov recently won the nobel prize under which category?
Silicon Valley Bank has been recently in the news.Who is the CEO of SVB?
By how much did the number of women seafarers increase from 2014 to 2024?