Let the total work = 24 units Efficiency of horse who can complete the work in 8 hours = 24/8 = 3 units/hour Efficiency of horse who can complete the work in 12 hours = 24/12 = 2 units/hour Therefore, time taken by both horses to complete the work together = 24/(3 + 2) = 4.8 hours Therefore, time taken by the elephant to complete the work = 4.8 hours