Question
A can do a work in 8 days and B in 12 days. If they work
on it together for 2 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (8, 12) = 24 unit 1 day’s work of A = 24/8 = 3 unit 1 day’s work of B = 24/12 = 2 unit 1 day’s work of (A + B) = 3 + 2 = 5 unit Now, 2 day’s work of (A + B) together = 2 × 5 = 10 unit Remaining work = 24 – 10 = 14 Remaining work completed by B = 14/2 = 7 days
Who lives immediate below P?
C visited the city on which of the following day of the week?
What is the position of E with respect to D?
Four of the following five are vishal in a certain way and hence form a group. Which is the one that does not belong to the group?
In each of the following questions, select the related word from the given alternatives:
OFFICE : QHHKEG ::WORKER : ?
Four of the following forms a group based on certain pattern. Who does not belong to this group?
Who among the following person visited on 9 May?
If D is related to Jaipur and G is related to Chennai in a certain way. Then, B is related to which of the following?
Who among the following live on topmost floor?
How many teams play between the teams which play game R and W?