Question
A and B together, B and C together and A and C
together can complete a piece of work in 13 days, 10 days and 14 days respectively. Find the ratio of the efficiencies of A, B and C, respectively.Solution
Let, the total work be 910 units (LCM of 13, 10 and 14)
Amount of work done by A and B together in one day = 910/13 = 70 units
Amount of work done by B and C together in one day = 910/10 = 91 units
Amount of work done by A and C together in one day = 910/14 = 65 units
Amount of work done by A, B and C together in one day = (70 + 91 + 65)/2 = 113 units
Amount of work done by A alone in one day = 113 – 91 = 22 units
Amount of work done by B alone in one day = 133 – 65 = 48 units
Amount of work done by C alone in one day = 133 – 70 = 43 units
So the desired ratio = 22:48:43
More Time and work Questions
Find the Value of β(-β3+β(3+8β(7+4β3)))?Β
What will come in the place of question mark (?) in the given expression?
888 + 777 - 666 = (? + 60) X 3 + 444
What will come in the place of question mark (?) in the given expression?
(18 Γ 8 Γ· 12) Γ 10 = ?
What will come in the place of question mark (?) in the given expression?
?2 - 222 = 900 Γ· 4 - β1089
- Simplify:

- What will come in place of the question mark (?) in the following questions?
0.5Γ120+25=? - What will come in the place of question mark (?) in the given expression?
389 + 641 - ? = 180 X 2 What will come in the place of question mark (?) in the given expression?
(40/25) X 80 - ? = 45% of 300 - 5519 × ? =361 ÷ 19
- Determine the value of following expression:
[{(148 + 32) Γ· 9}% x 1350] + 19