Question
‘X’ and ‘Y’ together can complete a work in 10 days, while ‘Y’ and ‘Z’ together can complete the work in 15 days. If ‘Y’ takes 12 days to complete the work alone then find the approximate time taken by all three together to complete 57.5% of work.
More Time and work Questions
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can Deepak...
- Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how many d...
- P and Q can complete a work in 28 days and 42 days, respectively. P, Q and R together can complete the work in 14 days. If R get a total wage of Rs. 5460 t...
- 12 men take 6 days to complete a piece of work. They worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will be ...
- ‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 2...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- 15 men can finish a work in 16 days by working 6 hours a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?
- A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- Aman and Bhuvan can complete a work in 21 days together, while Bhuvan alone can do it in 35 days. If the ratio of efficiencies of Aman and Chintu is 2:3, f...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)