Question
‘X’ and ‘Y’ together can
complete a work in 10 days, while ‘Y’ and ‘Z’ together can complete the work in 15 days. If ‘Y’ takes 12 days to complete the work alone then find the approximate time taken by all three together to complete 57.5% of work.Solution
Let the total work = 60 units
Efficiency of (X + Y) = 60/10 = 6 units/day
Efficiency of (Y + Z) = 60/15 = 4 units/day
Efficiency of ‘Y’ = 60/12 = 5 units/day
Efficiency of (X + Y + Z) = (6 + 4 – 5) = 5 units/day
Required time taken = (0.575 × 60)/5 = 7 days (approx)
More Time and work Questions
- Find the wrong number in the given number series.
9, 8, 18, 51, 208, 1045 Find the wrong number in the given number series.
1900, 1171, 669, 316, 100, - 25
75, 450, 225, 1330, 675, 4050
Find the wrong number in the given number series.
45, 68, 39, 70, 27, 74
A-5,  A,  35,  52, 78, 115
123, 155, 198, 246, 301, 363Â
- Find the wrong number, in the given number series.
2, 4, 12, 48, 240, 1440 - Find the wrong number in the given number series.
2, 6, 14, 30, 62, 126 - Find the wrong number in the given number series.
10, 26, 58, 106, 170, 258 1, 18, 44, 81, 131, 198