Question
Vijay can do a piece of work in 34 days and Sanjay can
do the same work in 51 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work will completed by Sanjay, then how much rupee Sanjay earned?Solution
Assume total work = LCM (34, 51) = 102 If the entire work is 102 units, Vijay can complete 3 unit per day, and Sanjay can complete 2 unit per days In 5 days, Vijay completes 15 units and got Rs. 1650 i.e. Rs.110 per unit. Remaining work = (102 – 15)unit = 87 unit ∴ Sanjay earning = Rs.87 × 102 = Rs. 9570
Which country will host the first Olympic Esports Games in 2027?
In the name "Aditya-L1," what does the term "L1" represent?
Which Union Minister launched the NATS 2.0 Portal in New Delhi?
Which institution has the National Payments Corporation of India (NPCI) partnered with through a long-term agreement to collaborate on research concerni...
Who was the first Indian to be elected as the leader of the Communist International in 1920?
What is “S-400”, sometimes seen in the news?
The UK has announced its decision to rejoin which EU's flagship scientific research scheme?
Which of the following is/are true in regards to National Quantum Mission (NQM):
1. Nurture and scale up scientific and industrial R&D Quantum Te...
International Day of United Nations Peacekeepers is observed annually on which day?
Which book contains the reference to the Mughal Emperor gifting a horse and elephant to Garh King Shyamshah?