πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A, B and C can complete a work in 10, 20 and 15 days

      respectively. A left the work 3 days before the work was completed and B left 1 days after A had left. The number of days required to complete the whole work is:
      A 84/13 Correct Answer Incorrect Answer
      B 72/17 Correct Answer Incorrect Answer
      C 85/13 Correct Answer Incorrect Answer
      D 100/9 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      A’s one day work = 1/10 B’s one day work = 1/20 C’s one day work = 1/15 Let total units of work be = 60 Efficiency of (A) = 6 Efficiency of (B) = 3 Efficiency of (C) = 4 Let ‘x’ days are required to complete the whole work. => 4x + 6(x-3) + 3(x-2) = 60 => 4x + 6x – 18 + 3x – 6 = 60 => 13x = 84 => x = 84/13 days

      Practice Next
      ask-question