Question
Arijit, Benny, and Chetna together can complete a work
in 12 days. If the ratio of the efficiency of Arijit, Benny, and Chetna is 8:5:6, respectively, then find the time taken by Arijit alone to complete the whole work.Solution
ATQ, Let the number of units of work done by Arijit, Benny and Chetna alone be 8a, 5a and 6a units per day, respectively. So, total work = 12 × (8a + 5a + 6a) = 228a units So, time taken by Arijit alone to complete the whole work = 228a/8a = 28.5 days
Bank of Baroda’s UPI-linked overdraft facility for women SHGs allows a maximum credit of:
With reference to ‘Old Pension Scheme’, consider the following statements:
I. Employees get a pension under a pre-determined formula which is...
_______ has approved a USD 250 million (about Rs 1,875 crore) loan to support India’s National Industrial Corridor Development Program (NICDP).
In which month and year will training for the initial projects under the India–UN Global Capacity Building Initiative begin?
What type of fossil preservation method was used for the dragonfly species Cordualadensa acorni?
What theme was the focus of the 62nd Session of the Commission for Social Development chaired by India?
Which village in Jammu & Kashmir was recognized in the Best Tourism Villages Competition 2024 under the Adventure Tourism category?
The Jallianwala Bagh Massacre took place in 1919. How many years of the massacre were commemorated on April 13, 2026?
As per Economic Survey 2025–26, while Census 2011 estimates India’s urban population at 31%, alternative estimates using the DEGURBA methodology sug...
Which sectors are restricted from FDI reclassification as per the new guidelines?