Question
C can do a piece of work in 20 days, and D can do the
same work in 25 days. They start working together, but after 8 days, C leaves. In how many more days will D finish the remaining work?Solution
Work done by C in 1 day = 1/20 Work done by D in 1 day = 1/25 Work done by C and D together in 1 day = (1/20) + (1/25) Taking LCM of 20 and 25 = 100, Work done together = (5/100) + (4/100) = 9/100 Work done in 8 days = 8 × (9/100) = 72/100 = 18/25 Remaining work = 1 - 18/25 = 7/25 D’s work rate = 1/25     Time taken by D to finish = (7/25) ÷ (1/25) = 7 days. Correct Option: c) 7 days
There are seven row houses, M, N, O, P, Q, R and S, in a campus, but not necessarily in the same sequence. P is not at any of the ends. R is to the imme...
If the sum of 48 and 52 is multiplied by 3, what will be the result?
In a certain code language, 'BSGN' is coded as '5-22-10-17' and 'TAUE' is coded as '23-4- 24-8'. How is 'PJDQ' coded in the given language?
In a code language, 'TRAIN' is written as ‘PKCTV’ and 'MESH' is written as 'JUGO'.
How will 'OMBRE' be written in that language?
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at variance...
Statement: Coal will remain in the largest single sources of power generation.
Select the correct statement from the given statements
Find the missing figure in the series from the given answer figures.
P, Q, R, S, T, U, and V live on seven different floors of the same building. The lowermost floor in the building is numbered 1, the floor above it is nu...
What will come in the place of the question mark (?) in the following equation, if '+' and '–' are interchanged and '×' and '+' are interchanged?
...Select the option that is related to the third figure in the same way as the second figure is related to the first figure.