Question
C can do a piece of work in 20 days, and D can do the
same work in 25 days. They start working together, but after 8 days, C leaves. In how many more days will D finish the remaining work?Solution
Work done by C in 1 day = 1/20 Work done by D in 1 day = 1/25 Work done by C and D together in 1 day = (1/20) + (1/25) Taking LCM of 20 and 25 = 100, Work done together = (5/100) + (4/100) = 9/100 Work done in 8 days = 8 × (9/100) = 72/100 = 18/25 Remaining work = 1 - 18/25 = 7/25 D’s work rate = 1/25     Time taken by D to finish = (7/25) ÷ (1/25) = 7 days. Correct Option: c) 7 days
In each of the following questions, a letter-number series is given with one or more terms missing as shown by (?). Choose the missing term out of the ...
Which of the following sequence represents the correct dictionary order of the following words?
1- Dual
2- Dwarf
3- Dubbing
...
Which of the following sequence represents the correct dictionary order of the following words?
1- Absolute
2- Abstract
3- Absolve
4- Absent
5- Abundant
Arrange the given words in the sequence in which they occur in the dictionary:
1. Manual
2. Manifest
3. MeaningÂ
4. Meeting
5. Menu
a) Nobilitary
b) Noblesse
c) Noble
d) Nobility
e) Nobble
Select the correct option that indicates the arrangement of the given words in the order in which they appear in an English dictionary.
1. Nation...
In each of the following questions, four options are given. Out of these, three are alike in a certain way, while one is different. Identify the odd on...
English dictionary.
1- Hyna
2- Hurt
3- Hurried
4- Hesitation
5- Higher
Which of the following sequences represents the correct dictionary order of the following words?
1. Chronicle
2. Chronic
3. Chronol...
Select the correct option that indicates the arrangement of given words in the order in which they appear in the English dictionary order.
1. Bio...