Question
Rs. 11200 was divided among A, B and C in the ratio
2:3:3. B kept Rs. 1000 for himself, gave Rs. 600 to his mother and divided the remaining money among his two sisters in the ratio 11:9. Then one of his sisters received:Solution
B’s share = Rs. 11200 × (3/8) = Rs. 4200 Money distributed between the two sisters, => Rs. [4200 – (1000 + 600)] = Rs. 2600 First sister’s share = Rs. 2600 × (11/20) = Rs. 1430 Second sister’s share = Rs. 2600 × (9/20) = Rs. 1170
Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% ...
Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work w...
A work can be completed by ‘A’ and ‘B’, alone in 7 days and 14 days, respectively. Find the number of days taken by ‘C’ to complete the same...
"Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but B...
8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women w...
Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed t...
'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Conseq...
'M' alone finishes a project in 30 days. 'M' and 'N' together can complete the same project in 16(2/3) days. How many days would 'N' need to do the proj...
A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same time during which the tank is ...
Before 'A' joined the team, 'S' and 'V' were alternating days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to fi...