Question
A certain number of men can complete a work in 50 days. If 10 more men are added, the work can be completed in 40 days. Find the original number of men.
More Quant Miscellaneous Questions
- Marked price of an article is Rs. M, as it is marked by a certain price. Find the value of M. Statement I. If the shopkeeper gives a discount of 10%, so, t...
- I. x2 + 31x + 238 = 0 II. 2y2 + 70y + 612 = 0
- Find the income of Rahul. Statement 1 : The saving of Rahul is Rs. 10,000 less than the saving of Piyush. Statement 2 : The ratio of income of Piyush to th...
- Select the option that is related to the third number in the same way as the second number is related to the first number. 15 : 3600 :: 7 : ?
- Two teams A and B can complete a road construction project in 18 days and 27 days respectively. They start working together, but after some days team B lea...
- A water tank has a capacity of 500 liters. A tap fills the tank at a rate of 10 liters per minute, while another tap empties it at a rate of 5 liters per m...
- Two pipes A and B can fill a tank in 15 hours and 20 hours, respectively. Another pipe C can empty the tank in 30 hours. If all three pipes are opened toge...
- A man invests ₹20,000 in a scheme that offers a 10% simple interest per annum. After how many years will his total amount become ₹30,000?
- Solve the equation: 2x² - 8x + 6 = 0.
- The ratio of the length and area of a rectangle is 1:39. And the ratio of length and breadth 4:3. Find the perimeter of the rectangle.
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)