Question

A can complete a certain work in 36 days. B is 33(1/3)% less efficient than A and C is 50% less efficient than
B. All the three started the work together, but A left 9 days after the start of the work and B left 3 days before the completion of the work. In how many days was the whole work completed?

A 32
B 28
C 29
D 30
Practice Next

Relevant for Exams:

Hey! Ask a query