Question
A can complete a certain work in 36 days. B is 33(1/3)% less efficient than A and C is 50% less efficient than
A can complete a certain work in 36 days. B is 33(1/3)% less efficient than A and C is 50% less efficient than
B. All the three started the work together, but A left 9 days after the start of the work and B left 3 days before the completion of the work. In how many days was the whole work completed?
More Previous year papers Questions
- Marked price of an article is Rs. 28500 and its selling price is Rs. 15675. What is the discount percentage?
- A shopkeeper bought a batch of shirts for ₹2,000. He sold 60% of the shirts at a 20% profit, and the remaining 40% of the shirts at a 10% loss. Find the ov...
- If x = 7 + 4√3 and xy = 1, then the value of (1x2+1y2)(1x2+1y2) is -
- Study the following bar graph and identify the modal day of the week:
- Find the value of y. x + y – z = 6 2x + y – z = 7 3x + y – 2z = 11
- Find the area of the rhombus with diagonals 45 cm and 30 cm.
- An article was sold at a loss of 18%. If it was sold for ₹2,475 more, then there would have been a profit of 12%. The cost price of the article is:
- (N+18) persons, each working for 7.5 hours a day, can complete 48% of a work in 20 days. (N+12) persons can complete the remaining work in 30 days, if each...
- Question 9
- Question 10
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)