    A can complete a certain work in 36 days. B is 33(1/3)%

    less efficient than A and C is 50% less efficient than B. All the three started the work together, but A left 9 days after the start of the work and B left 3 days before the completion of the work. In how many days was the whole work completed?
    A 32 Correct Answer Incorrect Answer
    B 28 Correct Answer Incorrect Answer
    C 29 Correct Answer Incorrect Answer
    D 30 Correct Answer Incorrect Answer

    Solution

    The correct answer is C